CompTIA PK0-005 sample questions with explanations, traps, topic labels, and IT Mastery route links.
These original sample questions are designed to help you check how the exam topics appear in decision-style prompts. They are not taken from the live exam.
Use these sample questions as a guided self-assessment for CompTIA Project+ (PK0-005) topics such as project lifecycle, stakeholder communication, change control, risks, issues, documents, governance, and IT delivery constraints. The prompts emphasize practical project judgment rather than vocabulary recall alone.
The sample set below is part of the CompTIA PK0-005 guide path:
Work through each prompt before opening the explanation. PK0-005 questions usually reward answers that preserve scope control, stakeholder alignment, traceability, and risk-aware delivery.
Topic: Handling a sponsor change request
A project sponsor asks the team to add a reporting dashboard halfway through execution. The dashboard is useful, but it was not in the approved scope. What should the project manager do first?
Best answer: C
Explanation: Project+ rewards disciplined change control. A useful change still needs impact analysis, documentation, approval, and baseline updates if accepted.
Why the other choices are weaker:
What this tests: change control, scope baseline, sponsor requests, impact analysis, and project governance.
Related topics: Change control; Scope; Governance; Stakeholders
Topic: Risk versus issue
A vendor warns that a required API may not be available before integration testing. Two weeks later the API is still unavailable and testing is blocked. How should the project records change?
Best answer: C
Explanation: A risk is a possible future event; an issue is a current problem requiring action. Once the API blocks testing, it needs issue ownership and active tracking.
Why the other choices are weaker:
What this tests: risk register, issue log, ownership, vendor blockers, and schedule impact.
Related topics: Risk; Issue log; Vendor; Schedule
Topic: Choosing the right status message
An executive sponsor asks whether the project is still on track. The schedule has slipped by one week, a mitigation plan is in progress, and a formal change may be needed if recovery fails. What is the best response?
Best answer: D
Explanation: Strong project communication is clear, factual, audience-aware, and action-oriented. Sponsors need impact and decisions, not optimism or raw detail.
Why the other choices are weaker:
What this tests: communication, status reporting, escalation, schedule variance, and stakeholder management.
Related topics: Status reporting; Communication; Escalation; Schedule
Tech Exam Lexicon and IT Mastery are independent study tools. They are not affiliated with, endorsed by, or sponsored by CompTIA or any certification body.