Project Risk, Issues, and Schedule Management

How to distinguish future risk from active issues, assess schedule impact, and manage owners, responses, float, and critical paths.

A risk is an uncertain future event that could affect objectives. An issue is a problem that has occurred and needs action. A change is a proposed alteration to an approved baseline. Classifying the situation correctly determines the appropriate record and response.

Situation Record and response
Possible future supplier delay Risk register, owner, likelihood, impact, response, and trigger
Vendor outage delaying today’s test Issue log, impact, owner, action, and escalation path
Approved scope must change Change request and impact analysis

The critical path is the sequence of dependent work that determines the earliest possible finish date. Float is the time an activity can slip without affecting a later milestone or completion date. Not every delay requires rebaselining; first assess dependencies, available float, and the impact on committed objectives.

Useful records make ownership visible: description, date, affected deliverables, severity or priority, owner, response, decision, due date, and current status.

Revised on Friday, September 11, 2026